ASTM A505:16 pdf download.Standard Specification for Steel, Sheet and Strip, Alloy, Hot-Rolled and Cold-Rolled,General Requirements for.
12.2 The identification shall be legibly stenciled on top of each lift or shown on a tag attached to each coil or shipping unit.
12.3 When specified on the order, each sheet shall be identified as agreed upon.
13. Retests
13.1 The retest provisions of Test Methods and Definitions A370 shall apply.
13.2 If the results of any tests do not conform to the specified requirements, (unless otherwise specified in the individual material speciflcation), retests may he made on double the original number of specimens from the same lot, each of which must conform to the requirements specified. If the results of the retests do not conform to the specified requirements, the lot shall he rejected.
14. Inspection and Testing
14.1 When the order specifies that the purchaser will inspect the material and witness testing, the inspector representing the purchaser shall have entry at all times while work on the contract of the purchaser is being performed, to all parts of the manufacturer’s works that concern the manufacture of the material ordered. The manufacturer shall afford the inspector all reasonable facilities to satisfy the inspector that the material is being furnished in accordance with the specification.
14.2 All tests (except product analysis) and inspection shall be made at the place of manufacture before shipment. unless otherwise specified on the order, and shall be so conducted as not to interfere unnecessarily with the operation of the works.
15. Rework and Retreatment
15.1 If inspection and test results fail to conform to the specified requirements, the material may he reworked or retreated, if the manufacturer can assure that the cause of failure is curable and that the quality of the material shall conform to the specified requirements. After retreatment, testing shall be done in accordance with the material specification requirements.
16. Rejection Subsequent to Shipment
16.1 Material that shows characteristics not in conformance with the material specification subsequent to its initial acceptance may be rejected. In such cases, the manufacturer should be notified in a timely manner.
17. Certification
17.1 When specified on the order, a certification of compliance shall he furnished that the material was manufactured, sampled. tested, and inspected in accordance with the requirements of the applicable specification.
17.2 When specified on the order, a report of the test results shall be furnished.